1. |
Employer |
: |
Ankara Metropolitan Municipality
General Directorate of Water and Sewage
Administration |
2. |
Name of the main work |
: |
Yenimahalle - Susuz village Istanbul road River
improvement in front of Tasis waste water and rain water sewage
Construction. |
3. |
Location of work |
: |
Ankara |
4. |
Construction Techniques Used |
: |
Trench excavations by machinery, hand leveling
and fine adjustment within the trenches, bedding and padding
with material,
laying of (Ø 200 - Ø 800) concrete and (Ø 1800 - Ø 2200)
reinforced concrete pipes, wrapping with material and backfilling.
All reinforced concrete boxes and setling basis by using
steel formwork with resulting fair faced concrete. |
5. |
Name and Surname of the relevant party |
: |
Seyfettin Oztas |
6. |
Title of the relevant party |
: |
Civil engineer |
7. |
To which title the certificate is issued |
: |
Site Chief |
8. |
Others working under the same title |
: |
None |
9. |
Preliminary amount of contract |
: |
650.000 USD |
10. |
Total amount of contract |
: |
950.000 USD |
11. |
Date of contract |
: |
14.08.2001 |
12. |
temporary acceptance date of the work |
: |
11.07.2002 |
13. |
first and last dates af service of the relevant
party |
: |
(22.08.2001– 15.07.2002) From beginning
until end of the work. |
14. |
Amount of work performed and percentage of
physical realization during the service of the relevant party |
: |
1.396.559,24 YTL %146,49 |
|
Amount of the Certificate |
: |
3.360.382 USD |
|
Amount of work performed |
: |
WW sewage network (Ø 200 -Ø800) |
: 5127m |
|
|
|
RW network (main collector) (Ø1800-Ø2200) |
: 1230m |
|
|
|
Box with Reinf. Conc. Cover ( 3,00 x 2,00 ) |
: 1109m |
|
|
|
Reinf. Concrete settling basins (1x2x2,5) |
: 12 ad |