All of the Spillway
Construction,
Production of
spillway access channel and slope concrete lining,
Final concrete
lining of derivation tunnel, inlet and outlet structures,
Supporting concrete
at the derivation tunnel,
Final concrete
lining of power tunnel, inlet and outlet structures,
Final concrete
lining of grouting galleries,
Construction of
outlet structure of the irrigation tunnel and slope linings,
Reinforced concrete
of pressure pipes,
Total construction
of a.b. power plant building (2 units, installed power 110 MW)
Power plant
building tail water discharge channel construction,
Construction of dam
security squadron headquarters building and dormitories,
Pump Station
Construction,
Dam crest top
arrangement and concrete,
Construction of
power plant access bridge on Dicle (Tigris) river,
Dam water level
measuring (Limnigraph) structure Construction,
Switch area and
open area concrete,
Water storage tank
construction, production of cable trays,
Siphon concrete,
Support wall
construction,
Various grills and
parapets,
TOTAL : 450.00 m3
concrete, 150.000 m2 formwork
and 50.000 tons steel production has been realized.
(The construction works of two derivation tunnels of (Ø
10 m) 717.20 m and 775.54 m, Irrigation tunnel of 740 m, Energy Tunnel
of 455 m, Injection and drainage gallery of (Ø
4,50 m) 4563 m, ventilation shaft of (Ø 3,20 m) 305) |