MAIN    ABOUT US    BUSINESS        REFERANCE    CONTACT    ARCHIVES   
 

Murat YILMAZ...

Photos of Dicle Dam Document of Work Experience (M.BAYINDIR)

Document of Work Experience (Kasmet Cons.)

Specifications of Dicle Dam and HEPP Installations Cons.

 

 

 

DOCUMENT OF WORK EXPERIENCE ( Work Inspection )

1.Employer

: General Directorate of Government Water Works

2.Name of Work

: Constructions of Dicle Dam and HEPP Installations

3.Place Work Done

: Egil / Diyarbakir

4.Technical of Applicated Construction

: Construction of Dam and Hydroelectric Power Station

a) Formation of clay stoned and rock filled dam body (2910000m3),

b) Total concrete and sliding mould systemed; hailsluice, watering, derivation, energy structures, pump station, approach slope coatings, formation of breakwater above body, Central HES construction, ‘salt’ zone, cable ducts, measure construction of water level, highway bridge of river transition, drinking water depot, kaptage, Gendarme Company Management Building, flat/house building, Managerial housing development buildings, watchman buildings, road ‘baks’ and cavities (540000 m3 concrete 7682 tones iron, 327000m2 mould production ),

c) Opened by drilling-exploding method; conjunction bloned, with conjunction, without conjunction, reinforced concrete coated, tunnel mould systemed and with different sizes derivation, watering, energy tunnels and injection galleries and cavity production ( 7257m tunnel 322m cavity),

d) Conjunction bloned (39800m) ve spraying concreted (201000 tones) slope endurance,

e) Prefabricated beamed hailsluice bridge and highway bridge with river transition.

f) Contact-consalidation injection works with sounding drill (223843m drill - 104170m3 injection) and slurry trench isolation partition (1707 m2)

g) Made by exploding or unexploding; art constructions, palye, slope, grazing, river improvement excavations, kaptage with cable ducts - water depot drinking water line construction (7500000m3 excavation),

h) Asphalt (10 km) and enduring (65 km) coated total 75 km communication roads and road of material stone construction,

ı) Mechanical constant equipment, entry grids, radial cover and lifting cover (2120tones) , algebra tube (3034tones), sliding butterfly conic valves, crown-door, strolling and monorail vinches, water emptying tubes, central building air conditioner airing fire electric telephone hygineic installations, whatever iron works (257 tones) and iron bridge construction,

j) Housing-development foundations and building works including steal construction and fixation roof coated whatever slim construction (building area 5071m2) zone-environment arranging and perimeter and relying upon walls by different sizes production.

5.   Name of concerned

: Murat YILMAZ

6.   Title of concerned

: Architect

7.   Document given as

: Construction Site Engineer

8.   Other personnels with same capacity

: Mustafa BAYINDIR (Civil Engineer) -Yesim  ERDEM  (Architect)

9.   Price of first agreement

: 15.312,50 YTL       (with price of 1985 year)

10.  Total price of agreement

: 53.886,73 YTL      (with price of 1985 year)

11.  Date of agreement

: 13.01.1986

12.  Ephemeral Acceptance Date of Work

: 24.07.2001

13.  Duty of concerned between

: 13.11.1990 – 24.07.2001

14.  Work completed when concerned in duty and its proportion

: 41.519,09 YTL  -  2,71

15.  Price of document

 : 203.057.710 USD

 

                                    

 

Kasmet Construction Industry Trade Incorporated Company